PROJECT PROGRESS

ROAD WORKS

Development 95%

Status:

SPINE ROAD (Main Road) Construction at 75%:

Current Works:

The spine road is now 75% complete. We are currently working on blinding and compaction to make the road motorable. Inverted drains and side slabs on the road are also 75% done, and road protection works like gabion boxes and gabion mattresses are 70% done.

CHAMPIONSHIP GOLF COURSE HOLE 1 - 18

Development 100%

Status: Complete

Migaa is a 18 Hole Championship Golf Course  accredited by the Kenya Golf Union in 2023.

Migaa’s par 72 has played host to the international pair tournament amongst many other tournaments.

The course has multiple tees ,obstacles which challenges the professional golfers while providing the upcoming golfer with an unforgettable experience.

BOUNDARY WALL

Development 100%

Status:

  • 6.3 KM Walling constructed – Overall progress at 100% Complete;
  • 2 Gate houses constructed to control the access to the development

 

 

 

 

ELECTRIC FENCE

Development 90%

Status:

Southern Boundary – 3.5 KMS: Erection of electric fence complete

Next Step:

Northern Boundary – 2.0 KMS : Construction of the power station to start soon

 

 

WATER SUPPLY

Development 87%

Status:

  • 6.3 KM Walling constructed – Overall progress at 100% Complete;
  • 2 Gate houses constructed to control the access to the development

 

 

 

 

SEWERAGE SYSTEM

Development 90%

Status:

Construction of line serving Mitini Scapes, Ubora Hospital, Sports Facility, Primary and Secondary school compete.

Next Step:

Sewer Treatment plant installation complete; to be commissioned.

 

 

HOME OWNERS

Development 70%

Status:

Completion of 200 units within the Migaa Estate

Next Step:

Home Owners continue to build their homes as we facilitate them with the resources required.

 

 

ICT

Development 90%

Status:

Phase 1: Internet connection to Mitini complete.

Current Works:

Phase 2: Provision of internet network on spine road, on going.

 

 

 

STREET LIGHTING

Development 90%

Status:

Phase 1: 90% complete.

Next Step:

Construction of street lighting for spine road, on going.

 

 

 

ENTRANCE STATEMENT

Development 90%

Status:

Phase 1: Complete. Gatehouses constructed to control the access to the development

Phase 2: Gatehouses to control the access to the development is complete.

 

 

 