Road Works
Status:
SPINE ROAD (Main Road) Construction at 75%:
Current Works:
The spine road is now 75% complete. We are currently working on blinding and compaction to make the road motorable. Inverted drains and side slabs on the road are also 75% done, and road protection works like gabion boxes and gabion mattresses are 70% done.
Golf Course Hole 1 - 9
Status:
Golf Course, construction in progress.
Current Works:
Grass planting on front nine is 100% complete. Irrigation is ongoing, to keep the grass healthy, lush and green. Grassing on hole 1 and 2 is continuing. Holes 4,5,6,7 and 8 are currently undergoing shaping.
Golf Course Hole 10 - 18
Status:
Back Nine Holes – (10,11,12,13, 14, 15, 16,17 &18)
- Construction and handover of the holes complete
- 4 Golf tournaments hosted in Migaa to date
- Open for resident and guest golfers
Boundary Wall
Status:
- 6.3 KM Walling constructed – Overall progress at 100% Complete;
- 2 Gate houses constructed to control the access to the development
Electric Fence
Status:
Southern Boundary – 3.5 KMS: Erection of electric fence complete
Next Step:
Northern Boundary – 2.0 KMS : Construction of the power station to start soon
Water Supply
Status:
Water reticulation works progress – 92% complete.
Drilling of 3 No. Boreholes complete and operational
Next Step:
2 No. borehole to have pump replaced
Sewerage System
Status:
Construction of line serving Mitini Scapes, Ubora Hospital, Sports Facility, Primary and Secondary school compete.
Next Step:
Sewer Treatment plant installation complete; to be commissioned.
Home Owners
Status:
Completion of 200 units within the Migaa Estate
Next Step:
Home Owners continue to build their homes as we facilitate them with the resources required.
ICT
Status:
Phase 1: Internet connection to Mitini complete.
Current Works:
Phase 2: Provision of internet network on spine road, on going.
Street Lighting
Status:
Phase 1: 90% complete.
Next Step:
Construction of street lighting for spine road, on going.
Entrance Statement
Status:
Phase 1: Complete. Gatehouses constructed to control the access to the development
Phase 2: Gatehouses to control the access to the development is complete.