Project Progress

Road Works

Development

Status:

SPINE ROAD (Main Road) Construction at 75%:

Current Works:

The spine road is now 75% complete. We are currently working on blinding and compaction to make the road motorable. Inverted drains and side slabs on the road are also 75% done, and road protection works like gabion boxes and gabion mattresses are 70% done.

Golf Course Hole 1 - 9

Development

Status:

Golf Course, construction in progress.

Current Works:

Grass planting on front nine is 100% complete. Irrigation is ongoing, to keep the grass healthy, lush and green. Grassing on hole 1 and 2 is continuing. Holes 4,5,6,7 and 8 are currently undergoing shaping.

Golf Course Hole 10 - 18

Development

Status:

Back Nine Holes – (10,11,12,13, 14, 15, 16,17 &18)

  • Construction and handover of the holes complete
  • 4 Golf tournaments hosted in Migaa to date
  • Open for resident and guest golfers

Boundary Wall

Development

Status:

  • 6.3 KM Walling constructed – Overall progress at 100% Complete;
  • 2 Gate houses constructed to control the access to the development

Electric Fence

Development

Status:

Southern Boundary – 3.5 KMS: Erection of electric fence complete

Next Step:

Northern Boundary – 2.0 KMS : Construction of the power station to start soon

Water Supply

Development

Status:

Water reticulation works progress – 92% complete.

Drilling of 3 No. Boreholes complete and operational

Next Step:

2 No. borehole  to have pump replaced

Sewerage System

Development

Status:

Construction of line serving Mitini Scapes, Ubora Hospital, Sports Facility, Primary and Secondary school compete.

Next Step:

Sewer Treatment plant installation complete; to be commissioned.

Home Owners

Development

Status:

Completion of 200 units within the Migaa Estate

Next Step:

Home Owners continue to build their homes as we facilitate them with the resources required.

ICT

Development

Status:

Phase 1: Internet connection to Mitini complete.

Current Works:

Phase 2: Provision of internet network on spine road, on going.

Street Lighting

Development

Status:

Phase 1: 90% complete.

Next Step:

Construction of street lighting for spine road, on going.

Entrance Statement

Development

Status:

Phase 1: Complete. Gatehouses constructed to control the access to the development

Phase 2: Gatehouses to control the access to the development is complete.